Five-level luxury mall marble atrium in Central, Hong Kong
Luxury Mall · Retail & Mall

Central Luxury Mall Marble Project

Five-level luxury mall in Central, Hong Kong · Full night-build marble programme

Project Overview

Project Overview

A five-level flagship mall in the heart of Central, Hong Kong — HENGSHENG delivered 28,000 sqm of marble works inside a trading mall through the full stone supply chain: quarry selection in Spain and Italy, 68 quality-inspection steps, factory pre-layout and 100% night-time installation. The scope covers the five-level atrium flooring, 24 round columns, lift-lobby feature walls and corridors, all handled end to end by one team for shop drawings, supply and installation.

📍
Central, Hong Kong
Location
📐
28,000 ㎡
Stone Area Installed
📅
9 months
Delivery Period
💎
3
Stone Varieties
🏬
Five-level atrium
Building Scale
📏
±1.5 mm
Flatness Control
🌙
100% night works
Working Pattern
Zero complaints
Owner Feedback
Looking up at the marble columns of the Central mall five-level atrium
Central Luxury Mall · Five-level atrium · 28,000 sqm marble works

Design Concept · A Marble Narrative Above the Atrium

Located in the heart of Central, Hong Kong, the five-level void atrium is the visual and pedestrian hub of the entire mall. HENGSHENG laid 18,000 sqm of Crema Marfil beige marble across all five levels to set a warm keynote; Calacatta Gold wraps the 24 round columns of the atrium, carrying continuous gold veining from the ground floor to the top level; Nero Marquina's black-and-white contrast defines the lift-lobby feature walls with understated luxury after dark.

Because the mall kept trading throughout the day, HENGSHENG delivered the entire chain — quarry selection, slab procurement, factory pre-layout and numbering, through to 100% night-time installation on site: 28,000 sqm of finished stone, 24 curved columns and dust-free dry-laying with full crystallisation, all digitally pre-laid and numbered in the factory for "arrive and install" delivery with zero re-working on site.

Applications

Atrium Column WrapsFlooringLift LobbiesCorridorsCeiling ProfilesService Counters
Materials

Stone Selection

Three top-grade marbles with clearly divided roles, supplied direct from Spanish and Italian quarries: Crema Marfil laid across 18,000 sqm of flooring over five levels sets the warm keynote of the whole project; Calacatta Gold wraps the 24 atrium columns as the visual centrepiece; Nero Marquina clads the lift-lobby feature walls, dramatic under evening lighting. Every slab passed 68 quality-inspection steps before leaving the factory.

Crema Marfil 米黃雲石大板MATERIAL 01
Crema Marfil
🇪🇸 Spain · Crema quarries
ApplicationFive-level flooring · 18,000 sqmFinishWarm beige tone · 20 mmStandard SizesSlab supply
Warm, uniform beige makes Spanish Crema Marfil the first choice for large commercial floors. Slabs from a single vein were factory pre-laid and blended so the 18,000 sqm of flooring across five levels reads as one continuous, colour-consistent surface with no visible banding.
View stone details →
Calacatta Gold 雲石大板 金色紋理MATERIAL 02
Calacatta Gold
🇮🇹 Italy · Carrara quarries
ApplicationAtrium columns · 24 round columnsFinishCurved panels · 20 mmStandard SizesSlab supply
Gold veining sweeps across a milky ground — among the rarest output of the Italian quarries. Five-axis CNC machined the slabs into curved panels wrapping all 24 atrium columns, so the veining runs continuously from the ground floor to the top level.
View stone details →
Nero Marquina 黑白閃電紋大板MATERIAL 03
Nero Marquina
🇪🇸 Spain · Markina quarries
ApplicationLift-lobby feature wallsFinishPolished · 20 mmStandard SizesSlab supply
White lightning across deep black carries real tension, and the contrast is dramatic under evening lighting. Every slab was numbered by veining direction, giving the lift-lobby feature walls 360° veining continuity — the most demanding single work package in the project.
View stone details →
Construction Process

Construction Process

The mall kept trading by day, so all works ran from 23:00 to 06:00. The programme advanced through six stages — night survey and setting-out, zone-by-zone shop-drawing layout, factory fabrication and numbering, night hoisting in batches, dust-free dry-laying with same-night grinding, and full crystallisation before opening. Every step carried its own data standards and signed accountability.

01

Night Survey & Setting Out

🌙
Night Survey & Setting Out

The mall trades by day; works ran only 23:00–06:00. 3D scanning built point-cloud models to absorb structural deviations in advance.

With the mall open throughout the day, every survey and setting-out task ran between 23:00 and 06:00; 3D laser scanners built point-cloud models zone by zone, overlaid on the design drawings to resolve structural deviations in advance.

02

Zone-by-Zone Shop-Drawing Layout

📐
Zone-by-Zone Shop-Drawing Layout

Five levels × 4 zones each, 20 work segments in total; factory pre-layout and numbering, piece-by-piece installation drawings.

The five levels were divided into four zones per level — 20 work segments in total — with deepened shop drawings, pre-layout and numbering completed in the factory, outputting piece-by-piece installation drawings so the site picks each slab by number with zero trial and error.

03

Factory Fabrication & Numbering

🏭
Factory Fabrication & Numbering

Slabs cut, sealed and numbered in the factory, packed in reverse installation order for zero on-site re-working.

Slabs were cut, sealed on six faces and numbered piece by piece in the factory, then packed in reverse installation order so they could be laid directly on arrival — avoiding secondary fabrication in the constrained night works.

04

Night Hoisting in Batches

🚚
Night Hoisting in Batches

Service lifts restricted to 01:00–04:00; materials hoisted in batches by work segment, staggered to keep daytime trading untouched.

Service-lift access was limited to 01:00–04:00, so materials moved in batches against a transport plan compiled by work segment — staggered logistics kept the mall fully open every day.

05

Dust-Free Dry-Laying + Same-Night Grinding

💨
Dust-Free Dry-Laying + Same-Night Grinding

Negative-pressure hoarding + low-noise cutting; grinding completed the same night, aisles reopened before the morning opening.

Negative-pressure hoarding and low-noise cutting controlled dust and noise; dry-laying was followed by grinding the same night, with the floor fully reopened before the mall opened the next morning.

06

Full Crystallisation Before Opening

Full Crystallisation Before Opening

Whole-floor crystallisation eliminated lippage; final flatness ±1.5 mm with uniform gloss.

Before the opening milestone the entire floor received unified crystallisation, eliminating lippage at the joints to a final flatness of ±1.5 mm with consistent gloss and tone.

Installation Details

Installation Details

Working inside a trading mall makes dust, noise and safety the first hurdles — alongside colour control across 28,000 sqm and 360° veining continuity on 24 round columns. Negative-pressure hoarding, low-noise cutting and a night-only workflow answered the operational interference, while same-vein blending, factory pre-layout and five-axis CNC curved panels secured the quality. Six key installation details below.

🛡️
Negative-Pressure Hoarding

Working inside a trading mall: hoarding with negative pressure locked dust inside each work segment, keeping public areas clean.

Negative-Pressure Hoarding

Each work segment was enclosed with negative-pressure hoarding, combined with wet working and air filtration to keep dust locked inside the work zone — the mall's daytime air quality was never affected.

🔇
Low-Noise Cutting

Night works used low-noise cutting equipment and damping pads, keeping noise within the mall's permitted range.

Low-Noise Cutting

Night works used low-noise cutting equipment with damping pads, paired with strict working-hour management to keep construction noise within the range acceptable to the mall and its neighbours.

🎨
Same-Vein Blended Laying

28,000 sqm at bulk scale: slabs from 6 batches of one vein blended, with factory pre-layout keeping the tone continuous.

Same-Vein Blended Laying

Colour control across 28,000 sqm was the core challenge; slabs from six batches of the same vein were blended and pre-laid in the factory, keeping the tone of the five-level flooring continuous and consistent.

🏛️
Five-Axis CNC Curved Column Panels

24 round columns machined into curved panels by five-axis CNC, assembled with temporary positioning rings for 360° veining continuity.

Five-Axis CNC Curved Column Panels

The curved panels for the 24 atrium columns were machined piece by piece by five-axis CNC from the 3D model, then calibrated on site with temporary positioning rings — 360° veining continuity with no layer breaks.

👣
Thickened 20 mm Anti-Slip Flooring

High-footfall flooring in thickened 20 mm slabs, surface treated to slip rating R10 — wear resistance and safety together.

Thickened 20 mm Anti-Slip Flooring

For heavy mall traffic the flooring used thickened 20 mm slabs for higher load and wear capacity; the surface was treated to slip rating R10, balancing safety with visual quality.

Nano Protection + Crystallisation

Whole-floor nano protective coating and crystallisation: stain-resistant and easy to clean, cutting the mall's long-term maintenance cost.

Nano Protection + Crystallisation

Before handover the whole floor received a nano protective coating and crystallisation, improving stain resistance and cleanability and significantly reducing the mall's long-term cleaning and maintenance cost.

Technical

Technical Highlights & Solutions

Working inside a trading mall, colour control across 28,000 sqm, 360° veining continuity on 24 round columns and wear resistance under heavy footfall form the project's four-fold engineering constraint. HENGSHENG resolved each in turn with negative-pressure hoarding, same-vein blending, five-axis CNC and thickened anti-slip finishing — key metrics and solutions below.

🌙
CHALLENGE 01

Working Inside a Trading Mall

The mall stayed open every day; dust, noise and site safety were the first concerns, and any disruption would hit tenants and footfall.

Solution: Negative-pressure hoarding locked down dust, low-noise cutting controlled noise, the entire workflow ran at night (23:00–06:00), and temporary hoarding with warning systems protected the public.
🎨
CHALLENGE 02

Colour Control Across 28,000 sqm

Supplying five levels in one programme, colour variation between quarry batches would show as visible bands at the joints.

Solution: Slabs from six batches of the same vein were blended, pre-laid and numbered in the factory, then laid to number on site — a continuous, consistent tone across the whole floor.
🏛️
CHALLENGE 03

360° Veining Continuity on 24 Round Columns

The curved panels wrapping the 24 atrium columns had to match vein around every column; a single misplaced panel breaks the whole column's visual.

Solution: Five-axis CNC machined each curved panel from the 3D model; temporary positioning rings calibrated assembly on site, achieving continuous 360° veining with no layer breaks.
👣
CHALLENGE 04

Wear Resistance Under Heavy Footfall

Daily crowds place strict demands on floor wear and slip performance; wear or slip hazards affect operations directly.

Solution: Thickened 20 mm slabs raised load and wear performance, the surface was treated to slip rating R10, and a nano protective agent cut long-term maintenance cost.
±1.5 mm
Measured flatness
28,000 sqm
Stone area installed
24
Atrium round columns
68
Quality-inspection steps
Get Started

Build Your Premier Project

Let Our Expert Team Serve You

Whatever the scale of your project, our engineering consultants will tailor the optimal stone solution for you — from material selection through to handover, with one-to-one service throughout.

By submitting you agree to our privacy policy. We will contact you within 24 hours.

Submission Successful!

Thank you for your enquiry. Our engineering consultant will contact you within 24 hours.

More

Explore More Projects

Browse more project case studies and discover HENGSHENG MARBLE S&T CO. LIMITED's excellence across every building type.